Published November 29, 2026 at 5:34 am | By Clarence Marshall

Water spilling through the gates of a hydroelectric dam beside its powerhouse

GREENWOOD, S.C. — Greenwood County’s plan to rebuild the flood-handling works at Buzzards Roost dam, the 1940 structure that holds back Lake Greenwood, now has a federal timeline. Staff at the Federal Energy Regulatory Commission intend to complete an environmental assessment of the project by Feb. 24, 2027.

The commission laid out that schedule in a notice dated Nov. 24 and filed Friday, Nov. 27. It is due to appear in the Federal Register on Monday, Nov. 30. The county owns the hydroelectric project, which is licensed by the commission as Project No. 1267, and it needs federal sign-off to change the license.

HERE CITY BUSINESS DIRECTORYOwn a business in Greenwood? Get listed HERE.One free listing per business, on its nearest HERE city. Premium features available.
ADD YOUR BUSINESS →

County officials asked for that change on Aug. 11. The goal is to let the dam pass very large floods safely. The request does not add generating capacity, and the county is not proposing any change to the dam’s normal operation or its generating equipment.

Five pieces of work are on the list. Crews would pour a new concrete emergency spillway just below the existing one, which is made of earth, and then rebuild that earthen spillway so water leaves the lake in a controlled way once floods reach set levels. The channel below it would be dug out so it can carry more water.

The plan also calls for a new berm in a low saddle of ground somewhere between 500 and 1,000 feet to the east, built to keep the lake from escaping there during a major flood. Concrete bulkhead walls at the powerhouse and at the service spillway would be raised so floodwater cannot spill over the top.

The county expects construction to begin in April 2027 and run for about a year.

The commission opened the request to public comment with a notice on Sept. 15 and gave the public until Oct. 15 to comment, ask to intervene or protest. Nobody filed anything in response.

Once the environmental assessment is finished, it will be posted for a 30-day comment period. Commission staff will weigh those comments before the commission rules on the amendment. The schedule can still shift.

The stakes are large for the region. Lake Greenwood covers about 11,400 acres along the Saluda River, stretches 21 miles and has 212 miles of shoreline in Greenwood, Laurens and Newberry counties. It is the area’s main spot for boating, fishing and lakefront living.

County Manager Toby Chappell, who has led the county staff since October 2012, is listed as the county’s contact on the filing. Residents who want help following the case can call the commission’s public participation office at (202) 502-6595. The docket number is P-1267-136.

BUSINESS SPONSOR — Bank of America — Local business banking, nationwide reach
BUSINESS BANKING →
📅 This space available in 3 days — local advertisers get priority. Claim it →

Section: More Greenwood SC business news

Greenwood business profiles

Filed under: Greenwood SC Business News

What's Happening
What is changing at Buzzards Roost dam?
Greenwood County wants a new concrete emergency spillway, a rebuilt earthen spillway, a deeper spillway channel, a new flood berm and taller bulkhead walls so the dam can pass very large floods.
When will the federal review be done?
Federal Energy Regulatory Commission staff plan to finish the environmental assessment by Feb. 24, 2027, followed by a 30-day comment period.
When would construction start?
The county expects work to begin in April 2027 and take about 12 months.
Clarence Marshall
HERE Greenwood · BUSINESS

Clarence writes for HERE Greenwood.

Contact Clarence
HEREmention Get Your Business Found in AI BE THE ANSWER. When customers ask ChatGPT, Perplexity, or Google AI who to hire — your name comes up. Learn More

BUSINESS NEWS NEAR GREENWOOD SC

Business coverage from the 10 closest HERE cities.